State Highway 2 between Wairoa and Napier will be open around the clock from Wednesday.
This stretch of highway suffered devastation during Cyclone Gabrielle, with damage to around 100 sites, including the Devil鈥檚 Elbow and Waikare Gorge bridge.
Following completion of the Waikare Gorge Bailey bridge, the highway opened to daytime traffic a fortnight ago.
Waka Kotahi regional manager of maintenance and operations Jaclyn Hankin said the road had been closed to night-time traffic since it reopened to help keep motorists safe.
鈥淥ur contractors worked incredibly hard to reopen the road to daytime traffic earlier this month but we needed more time to ensure the road was as safe as it could possibly be for night-time traffic.
鈥淚t still looks very different to what it looked like before the cyclone, however. Over the past few weeks, our contractor has installed guardrail, reflective cat eyes, safety poles and additional cones to make the section through Devil鈥檚 Elbow safe for overnight travel.
鈥淲e鈥檝e also used the extra fortnight to complete strengthening work at Esk River Bridge on SH2, just north of the turn off to Taup艒.
鈥淐ompleting work at the bridge has meant the 30km/h temporary speed restriction has been lifted.鈥
A section near the Devil's Elbow on State Highway 2 between Napier and Wairoa which will reopen 24 hours a day. Photo / Waka Kotahi
On Tuesday night, crews will use the final night closure to reseal the road at Waikoau Hill where a major underslip site was repaired just before the cyclone.
Hankin says despite this progress, there is still significant work to do 鈥 most of which is dependent on favourable weather conditions and therefore, likely to be completed in spring and summer.
鈥淚n the meantime, work to maintain access and levels of service will continue throughout the winter months.
鈥淭here will still be temporary speed restrictions and stop/go controls in a number of places. Please be aware of the conditions, take care, don鈥檛 rush and abide by the traffic controls in place.
鈥淥pening this vital connection has been a huge step forward in our cyclone recovery work and being able to extend the opening to 24/7 is another boost for freight and the communities that rely on this key connection between Hawke鈥檚 Bay and Tair膩whiti.
鈥淲e want to reiterate our gratitude to everyone travelling this road for their patience 鈥 it鈥檚 been a trying time, and we鈥檙e delighted to take another step toward a return to normality.鈥
Take your Radio, Podcasts and Music with you
Get the iHeart App
Get more of the radio, music and podcasts you love with the FREE iHeartRadio app. Scan the QR code to download now.
Download from the app stores
Stream unlimited music, thousands of radio stations and podcasts all in one app. iHeartRadio is easy to use and all FREE